A pipefitter is preparing to perform hot work on a 6-inch carbon steel line that previously carried a flammable hydrocarbon. The line has been purged with nitrogen and a combustible gas detector reads 0% LEL. Which additional step is MOST critical before issuing a hot work permit?
-
A
Verify that the oxygen content of the nitrogen-purged line is between 19.5% and 23.5% before welding begins
-
B
Confirm the line has been physically isolated with a blind or spectacle blind, and verify oxygen-deficiency hazard controls are in place for workers entering the area
-
C
Perform a second LEL reading 15 minutes after the first to confirm the reading is stable
-
D
Apply heat-resistant insulation to adjacent piping within 3 feet of the hot work area