Certified Management Accountant Risk Management 3 — Questions and Answers
Question 1: The COSO ERM framework identifies how many interrelated components?
- Five
- Six
- Eight (Correct answer)
- Ten
Correct answer: Eight
The original COSO ERM framework (2004) consists of eight interrelated components, later updated in 2017 to five components.
Question 2: A manufacturer decides to discontinue a product line because the liability risk is too high. This risk response is called:
- Risk mitigation
- Risk transfer
- Risk avoidance (Correct answer)
- Risk acceptance
Correct answer: Risk avoidance
Risk avoidance eliminates the risk entirely by deciding not to engage in the activity that creates the risk.
Question 3: Key Risk Indicators (KRIs) are best used to:
- Quantify residual risk after controls
- Provide early warning signals of increasing risk exposure (Correct answer)
- Assign accountability for individual risks
- Calculate the expected monetary value of a risk event
Correct answer: Provide early warning signals of increasing risk exposure
KRIs are forward-looking metrics that signal when risk levels are trending toward unacceptable thresholds.
Question 4: Which term describes the risk that remains after management has implemented controls?
- Inherent risk
- Residual risk (Correct answer)
- Secondary risk
- Control risk
Correct answer: Residual risk
Residual risk is the level of risk exposure remaining after controls and other risk responses have been applied.
Question 5: An organization's risk tolerance differs from risk appetite in that risk tolerance refers to:
- The strategic goals that drive risk-taking behavior
- The maximum acceptable variation around an objective before action is required (Correct answer)
- The process used to rank risks by priority
- The probability that a given risk event will occur
Correct answer: The maximum acceptable variation around an objective before action is required
Risk tolerance is the acceptable deviation from risk appetite — the operational boundary within which management must stay.
Question 6: Which of the following best describes a 'black swan' event in risk management?
- A highly predictable risk with known probability
- A risk that has been fully mitigated through insurance
- A rare, unpredictable event with severe consequences (Correct answer)
- A risk accepted within normal business tolerance
Correct answer: A rare, unpredictable event with severe consequences
Black swan events are extreme outlier occurrences that are nearly impossible to predict but have massive impact when they occur.
Question 7: Scenario analysis in risk management is primarily used to:
- Calculate the exact probability of a single risk event
- Evaluate how an organization would perform under different hypothetical conditions (Correct answer)
- Identify which employees are responsible for specific risks
- Determine the market value of assets at risk
Correct answer: Evaluate how an organization would perform under different hypothetical conditions
Scenario analysis tests organizational resilience by modeling responses to various plausible future states.
The COSO ERM framework identifies how many interrelated components?