The variable overhead spending variance measures:
-
A
The difference between actual variable OH rate and standard rate, applied to actual hours worked
-
B
The efficiency with which inputs were used relative to standard inputs allowed
-
C
The total under- or over-applied variable overhead for the period
-
D
The difference between budgeted fixed OH and actual fixed OH incurred