In a standard costing system, the materials price variance is calculated as:
-
A
(Actual price − Standard price) × Actual quantity purchased
-
B
(Actual price − Standard price) × Standard quantity allowed
-
C
(Standard price − Actual price) × Standard quantity used
-
D
(Actual quantity − Standard quantity) × Standard price