An internal auditor discovers a significant control deficiency during a field review. Which communication action should occur FIRST?
-
A
Draft the final audit report immediately
-
B
Discuss the finding with the process owner to validate facts
-
C
Escalate directly to the audit committee without delay
-
D
Notify external regulators of the deficiency