Agile Metrics & Reporting Flashcards
7 cards from real CAE practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Agile Metrics & Reporting flashcards as text
In scaled agile environments, which metric helps leadership understand whether teams are aligned toward a common program goal?
Answer: Program Increment (PI) objectives completion rate
PI objectives completion rate at the program level shows how well multiple teams collectively achieve shared business outcomes across a planning increment.
A Scrum team consistently finishes sprints under capacity and wants to improve forecasting. Which approach should they take FIRST?
Answer: Analyze historical velocity to establish a realistic planning range
Reviewing historical velocity data gives the team empirical evidence to set a realistic planning range rather than over- or under-committing.
What is the PRIMARY purpose of an agile 'information radiator'?
Answer: To make team progress and key metrics visible to all stakeholders at a glance
Information radiators are large, visible displays that broadcast team metrics and progress transparently to everyone in the environment, fostering accountability.
Which statement about story point estimation is MOST accurate?
Answer: Story points are relative measures of effort, complexity, and uncertainty
Story points represent relative size combining effort, complexity, and risk—they are not hours and should not be compared directly across different teams.
A team notices their cycle time has been increasing steadily over four sprints despite stable velocity. What is the MOST likely root cause?
Answer: Technical debt is slowing down individual work items even if overall output stays constant
Growing technical debt commonly increases the time each item takes to complete (cycle time) without necessarily reducing the count of items completed (velocity).
When should an agile team recalibrate their velocity baseline?
Answer: After significant team composition changes such as adding or losing members
Velocity is team-specific; when team membership changes significantly, the historical baseline no longer reflects the current team's capacity and should be reset.
Which type of agile report gives a product owner the CLEAREST picture of total work remaining against a fixed release date?
Answer: Release burnup chart
A release burnup chart shows both total scope and completed work over time, making it easy to see if the team is on track to meet a release date.