CEPSCI Cheat Sheet 2026
The 30 highest-yield CEPSCI facts, distilled from real exam questions. Print it, save it as a PDF, or study it here — free, no sign-up.
80 questions
180 min time limit
75% to pass
- Which particle size is the most difficult to remove in a sediment basin? → Clay and fine silt particles
- Which soil textural class is generally considered most erodible by water? → Silt and fine sand
- PAM is a chemical that is added to turbulent runoff primarily to achieve the following. → Cause flocculation that reduces sediment transport.
- During site assessment, a CEPSCI inspector should evaluate the site's proximity to: → Water bodies, wetlands, and sensitive receiving waters
- Why should the embankment of a temporary sediment basin be inspected after every significant storm? → To identify signs of seepage, settlement, or erosion that could lead to embankment failure
- Which of the following is a source control BMP rather than a treatment BMP? → Phased construction limiting the area of disturbance
- If a state regulatory inspector visits a construction site and the SWPPP is not available, the likely consequence is: → A notice of violation that may result in fines for failure to maintain required records
- What is the recommended inspection frequency for erosion and sediment controls after construction begins? → At least once a week or within 24 hours of the end of a storm event >0.5 inches.
- A grab sample collected for turbidity monitoring at a construction site should ideally be taken: → During a storm event when discharge is actively occurring
- What is the typical acceptable turbidity benchmark for construction site discharges under many state NPDES permits before further action is required? → 250 NTU
- To whom are NPDES permits typically issued? → Operators or companies responsible for a specific discharge.
- A construction inspector observes that discharge turbidity is 320 NTU and the benchmark is 250 NTU. What is the required response under the EPA CGP? → Document the exceedance and immediately review and modify the SWPPP and BMPs
- Where are sediment tubes typically installed to reduce soil erosion and retain sediment? → In drainage conveyance swales as ditch checks.
- A bioswale differs from a conventional drainage swale primarily because it: → Uses engineered soil and vegetation to filter and infiltrate runoff while conveying it
- Final site stabilization is achieved when the percent vegetative cover on all disturbed areas is at least the following. → 70 percent
- The wet storage volume in a sediment basin is designed to: → Hold the accumulated sediment load between cleanout events
- Which factor is NOT typically evaluated during a site's pre-construction erosion control assessment? → Adjacent property owner's personal finances
- Why is it important to minimize runoff velocity on a construction site? → Lower velocity reduces the erosive energy that detaches and transports soil particles
- The principal spillway of a sediment basin should be sized to pass the: → Design storm flow while maintaining water quality treatment in the basin
- The main benefit of using mulches and ECBs is that they: → Provide instant cover
- A pipe slope drain is used to: → Convey runoff down a steep slope in a controlled manner without causing erosion
- What is the recommended aggregate size for a stabilized construction entrance? → Coarse aggregate 1.5 to 3 inches in diameter
- How does impervious surface coverage affect stormwater runoff on a site? → It increases runoff volume and velocity by preventing infiltration
- After construction is complete, what triggers the requirement to remove temporary BMPs such as silt fences? → Achievement of final stabilization of all disturbed areas and formal permit termination
- The emergency spillway of a sediment basin is designed to: → Safely pass flows from storms exceeding the design storm without causing basin failure
- What is a rip rap channel typically used for? → Preventing soil movement with erosion-resistant stone lining.
- What is a 'construction entrance' or 'stabilized pad' BMP designed to do? → Remove mud and dirt from vehicle tires before they exit the site onto public roads
- What soil amendment is most commonly applied before seeding to improve germination on disturbed sites? → Lime and fertilizer based on soil test results
- A soil's NRCS Hydrologic Soil Group classification affects site planning because it indicates: → The soil's runoff potential and infiltration rate
- A site drainage map is used during site assessment to: → Identify natural drainage patterns and flow paths that may concentrate runoff
Turn these facts into recall: