A project manager notices the critical path has shifted after a schedule update. What is the most likely cause?
-
A
A budget overrun on a non-critical activity
-
B
Actual durations differing from estimates, consuming float on previously non-critical paths
-
C
A change in project scope
-
D
The addition of new resources to critical activities