Which of the following best describes the 'learning curve' effect in cost estimating?
-
A
Costs increase as workers become more familiar with a task
-
B
Unit costs decrease by a constant percentage each time cumulative output doubles
-
C
Overhead rates decline as project scope grows
-
D
Material costs stabilize after the first procurement cycle