CEP Contract Documentation & Legal Considerations 2 — Questions and Answers
Question 1: Which contract clause establishes the priority order when conflicts exist between different contract documents?
- Order of precedence clause (Correct answer)
- Integration clause
- Severability clause
- Force majeure clause
Correct answer: Order of precedence clause
An order of precedence clause specifies which contract document governs when contradictions exist between drawings, specifications, and other documents.
Question 2: A 'no damages for delay' clause in a construction contract typically means the contractor:
- Can only recover extended overhead costs
- Can only recover time, not additional money, for owner-caused delays (Correct answer)
- Cannot recover anything for any delay regardless of cause
- Can terminate the contract after 30 days of delay
Correct answer: Can only recover time, not additional money, for owner-caused delays
A no-damages-for-delay clause limits the contractor's remedy for owner-caused delays to a time extension only, not additional compensation.
Question 3: What is the primary purpose of a 'liquidated damages' provision in a contract?
- To penalize the contractor for poor quality
- To provide a predetermined compensation amount for specific breaches such as schedule delays (Correct answer)
- To cap the owner's total liability
- To establish the contractor's profit margin
Correct answer: To provide a predetermined compensation amount for specific breaches such as schedule delays
Liquidated damages clauses establish a pre-agreed daily or weekly amount the contractor owes the owner for failure to complete by the contract completion date.
Question 4: Under the Miller Act, payment bonds on federal construction projects are required when the contract value exceeds:
- $25,000
- $100,000
- $150,000 (Correct answer)
- $500,000
Correct answer: $150,000
The Miller Act requires performance and payment bonds on federal construction contracts exceeding $150,000.
Question 5: A 'cardinal change' to a construction contract is best described as:
- A change order exceeding 10% of the contract value
- A modification so substantial it fundamentally alters the scope of the original contract (Correct answer)
- Any change issued after 50% project completion
- A change requiring congressional approval on public projects
Correct answer: A modification so substantial it fundamentally alters the scope of the original contract
A cardinal change is one so drastic that it cannot be considered part of the original contract, potentially allowing the contractor to treat it as a breach.
Question 6: Which document typically defines the procedures for submitting and resolving contractor claims for additional compensation?
- The project schedule
- General Conditions of the contract (Correct answer)
- The bid instructions
- The subcontract agreement
Correct answer: General Conditions of the contract
General Conditions (e.g., AIA A201 or FAR clauses) establish the formal procedures, notice requirements, and time limits for submitting claims.
Question 7: When an estimator reviews a 'mutual waiver of consequential damages' clause, what risk is being addressed?
- Protection against liens filed by subcontractors
- Limiting recovery for lost profits, loss of use, or business interruption damages by both parties (Correct answer)
- Waiving the right to file arbitration
- Excluding warranties on installed materials
Correct answer: Limiting recovery for lost profits, loss of use, or business interruption damages by both parties
A mutual waiver of consequential damages protects both owner and contractor from claims for indirect losses like lost profits or business interruption beyond direct project costs.
Which contract clause establishes the priority order when conflicts exist between different contract documents?