An electrical inspector performing a pre-inspection plan review notices that load calculations are missing from the submitted documents. The inspector should:
-
A
Proceed with the inspection and note the omission verbally
-
B
Approve the inspection contingent on load calculations being provided later
-
C
Reject the permit application and require complete documents before scheduling inspection
-
D
Perform a field load calculation using the installed equipment