← All CEC Flashcard Decks

Overhead & Profit Calculation Flashcards

7 cards from real CEC practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Overhead & Profit Calculation flashcards as text
  1. A contractor uses the 'cost-plus' method and charges the owner actual costs plus 15% overhead and 10% fee. If actual direct costs are $200,000, what does the owner pay?

    Answer: $253,000

    Overhead = $30,000; Fee = 10% × ($200,000 + $30,000) = $23,000; Total = $200,000 + $30,000 + $23,000 = $253,000.

  2. Which financial statement is MOST useful for verifying that overhead costs used in an estimate align with actual company performance?

    Answer: Income statement (profit and loss)

    The income statement shows actual revenue and expense categories including overhead, enabling comparison with estimated overhead rates.

  3. A contractor estimates $40,000 in profit on a $500,000 project. Midway through, scope changes add $50,000 in direct costs. If no change order adjustment is made to the profit, what is the new profit percentage?

    Answer: 7.3%

    $40,000 ÷ $550,000 = 7.27%, approximately 7.3%.

  4. What is the purpose of a 'contingency' in an estimate, and how does it differ from profit?

    Answer: Contingency covers unknown or uncertain costs; profit is the reward for successful project management

    Contingency addresses cost uncertainties and scope gaps, while profit is the contractor's intended return on investment.

  5. A company's overhead costs are 18% of direct costs and profit goal is 10% of direct costs. What single markup percentage on direct costs achieves both?

    Answer: 28%

    Simply add the two percentages: 18% overhead + 10% profit = 28% combined markup on direct costs.

  6. Which of the following would DECREASE a contractor's required overhead recovery rate?

    Answer: Increasing annual construction volume

    Increasing volume spreads fixed overhead across more projects, reducing the percentage needed from each project.

  7. An estimator is preparing a bid for a $1,000,000 project. The company policy requires a minimum 6% net profit on revenue. What is the minimum acceptable net profit amount?

    Answer: $60,000

    6% of $1,000,000 revenue = $60,000 minimum net profit.