← All CEC Flashcard Decks

Overhead & Profit Calculation Flashcards

7 cards from real CEC practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Overhead & Profit Calculation flashcards as text
  1. A contractor wants a 12% profit on the selling price (not cost). If direct costs plus overhead total $88,000, what should the bid price be?

    Answer: $100,000

    Bid price = $88,000 ÷ (1 − 0.12) = $88,000 ÷ 0.88 = $100,000.

  2. Which of the following best describes the break-even point for a construction company?

    Answer: The revenue level at which total costs equal total income with zero profit

    Break-even is when total revenue exactly covers all costs—direct and overhead—leaving zero net profit.

  3. A contractor's job overhead for a project includes: superintendent salary $15,000, portable toilets $600, temporary power $1,200, and job trailer $2,400. What is the total job overhead?

    Answer: $19,200

    $15,000 + $600 + $1,200 + $2,400 = $19,200.

  4. Why might a contractor apply a HIGHER profit margin on a risky or complex project?

    Answer: To account for the increased likelihood of cost overruns and uncertainties

    Higher risk projects warrant higher profit margins to compensate for potential cost overruns and uncertainties.

  5. If a contractor's markup on cost is 25%, what is the equivalent margin (profit as a percentage of selling price)?

    Answer: 20%

    Margin = markup ÷ (1 + markup) = 0.25 ÷ 1.25 = 20%.

  6. A contractor's annual fixed overhead is $300,000. If volume increases by 20% next year with no change in overhead, what happens to the overhead rate per dollar of direct cost?

    Answer: It decreases by approximately 17%

    Higher volume spread over fixed overhead reduces the overhead rate; $300,000 ÷ (1.2 × base) = rate drops ~17%.

  7. On a lump-sum contract, where does the risk of overhead cost overruns primarily fall?

    Answer: The contractor

    On a lump-sum contract, the contractor bears the risk if actual overhead exceeds the estimated amount included in the bid.