Overhead & Profit Calculation Flashcards
7 cards from real CEC practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Overhead & Profit Calculation flashcards as text
A contractor wants a 12% profit on the selling price (not cost). If direct costs plus overhead total $88,000, what should the bid price be?
Answer: $100,000
Bid price = $88,000 ÷ (1 − 0.12) = $88,000 ÷ 0.88 = $100,000.
Which of the following best describes the break-even point for a construction company?
Answer: The revenue level at which total costs equal total income with zero profit
Break-even is when total revenue exactly covers all costs—direct and overhead—leaving zero net profit.
A contractor's job overhead for a project includes: superintendent salary $15,000, portable toilets $600, temporary power $1,200, and job trailer $2,400. What is the total job overhead?
Answer: $19,200
$15,000 + $600 + $1,200 + $2,400 = $19,200.
Why might a contractor apply a HIGHER profit margin on a risky or complex project?
Answer: To account for the increased likelihood of cost overruns and uncertainties
Higher risk projects warrant higher profit margins to compensate for potential cost overruns and uncertainties.
If a contractor's markup on cost is 25%, what is the equivalent margin (profit as a percentage of selling price)?
Answer: 20%
Margin = markup ÷ (1 + markup) = 0.25 ÷ 1.25 = 20%.
A contractor's annual fixed overhead is $300,000. If volume increases by 20% next year with no change in overhead, what happens to the overhead rate per dollar of direct cost?
Answer: It decreases by approximately 17%
Higher volume spread over fixed overhead reduces the overhead rate; $300,000 ÷ (1.2 × base) = rate drops ~17%.
On a lump-sum contract, where does the risk of overhead cost overruns primarily fall?
Answer: The contractor
On a lump-sum contract, the contractor bears the risk if actual overhead exceeds the estimated amount included in the bid.