A hospital's power factor is measured at 0.78 lagging. Its tariff imposes a power factor penalty below 0.90. Which action would most directly eliminate this penalty?
-
A
Installing additional lighting load to increase kWh consumption
-
B
Adding capacitor banks to supply reactive power locally
-
C
Switching to a time-of-use rate schedule
-
D
Negotiating a demand ratchet waiver with the utility