CEA Measurement & Verification (M&V) Protocols Flashcards
6 cards from real CEA practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 6 CEA Measurement & Verification (M&V) Protocols flashcards as text
Which organization publishes the International Performance Measurement and Verification Protocol (IPMVP)?
Answer: EVO (Efficiency Valuation Organization)
The Efficiency Valuation Organization (EVO) publishes and maintains the IPMVP, the globally recognized framework for M&V of energy savings.
In M&V terminology, what is the 'baseline period'?
Answer: The reference period before efficiency measures are implemented, used to establish pre-retrofit energy use
The baseline period represents energy consumption before efficiency measures are applied, serving as the reference against which post-retrofit savings are measured.
IPMVP Option A (Retrofit Isolation – Key Parameter Measurement) involves what approach?
Answer: Measuring some parameters and stipulating others based on short-term or historical data
Option A measures key performance parameters (e.g., power draw) while stipulating less critical parameters (e.g., operating hours) from historical data.
IPMVP Option B (Retrofit Isolation – All Parameter Measurement) differs from Option A in that it:
Answer: Continuously meters all relevant parameters of the isolated system rather than stipulating any
Option B requires continuous measurement of all parameters (power and hours) for the specific system, providing higher accuracy than Option A but at greater monitoring cost.
What is a 'stipulation' in the context of IPMVP M&V?
Answer: A value assumed or agreed upon rather than directly measured, used to simplify M&V
A stipulation is an agreed-upon value for a parameter (like operating hours) that is not directly measured, accepted by both parties to reduce M&V costs.
Which IPMVP option is most appropriate when energy savings cannot be attributed to isolated systems and whole-building metering is required?
Answer: Option C
Option C (Whole Facility) uses utility meter data to track savings at the whole-building level, suitable when measures affect overall facility consumption.