What is the term for a conduit bend that rises from a horizontal run to connect to a box mounted on a wall?
Answer: Kick
A kick is a single bend that angles a conduit run to meet a box or enclosure offset from the original run direction.
When bending a three-bend saddle around a 2-inch obstruction, what are the three bend angles typically used?
Answer: 22.5°, 45°, 22.5°
A three-bend saddle uses 22.5°, 45°, and 22.5° bends to clear an obstruction while keeping the conduit run parallel.
The multiplier used to calculate the distance between bends when making a 30-degree offset is approximately:
Answer: 2.000
A 30-degree offset uses a multiplier of 2.0; the distance between bends equals the offset height multiplied by 2.0.
Rigid Metal Conduit (RMC) differs from Intermediate Metal Conduit (IMC) primarily in:
Answer: Wall thickness and weight
RMC has thicker walls than IMC, making it heavier but providing greater mechanical protection in harsh environments.
What does the 'shrink' of a conduit offset refer to?
Answer: The reduction in overall run length caused by the offset
Shrink is the amount by which a conduit run is shortened along its axis when an offset is added; it must be added to the mark location to hit the target.
PVC conduit installed outdoors and exposed to direct sunlight must be:
Answer: Listed as sunlight-resistant
NEC 352.12 requires that PVC conduit exposed to sunlight be listed as sunlight-resistant to prevent UV degradation.
What is the correct method for cutting threads on rigid metal conduit in the field?
Answer: Use a pipe threader with the correct die size and thread cutting oil
Field threading requires a properly sized die and cutting oil to produce clean, accurate NPT threads without damaging the conduit.