An economic analyst is conducting a cost-benefit analysis for a proposed public infrastructure project.
The project has a present value of total benefits estimated at $80 million and a present value of total costs estimated at $65 million.

Based on the standard decision rule, what is the Net Present Value (NPV) of the project and what is the appropriate recommendation?