CDT Project Planning & Scheduling 3 — Questions and Answers
Question 1: In PERT (Program Evaluation and Review Technique), the expected time formula uses optimistic (O), pessimistic (P), and most likely (M) estimates. The formula is:
- (O + M + P) / 3
- (O + 4M + P) / 6 (Correct answer)
- (O + 2M + P) / 4
- (O + M + P) / 4
Correct answer: (O + 4M + P) / 6
The PERT weighted average formula is (O + 4M + P) / 6, giving the most likely estimate four times the weight.
Question 2: A drafting project has a baseline schedule. After the client requests additional drawing revisions, the project manager issues a revised schedule. What document authorizes the scope change?
- A project status report
- A change order or change request (Correct answer)
- A risk register update
- A punch list
Correct answer: A change order or change request
A change order formally documents, authorizes, and tracks scope changes that affect the schedule, cost, or deliverables.
Question 3: Which scheduling format best shows the relationship between tasks and calendar dates while also indicating task duration as a bar?
- Network diagram
- Gantt chart (Correct answer)
- PERT chart
- Responsibility matrix
Correct answer: Gantt chart
Gantt charts display tasks as horizontal bars along a timeline, clearly showing start dates, durations, and end dates.
Question 4: A project schedule baseline serves primarily as:
- The initial rough estimate before client approval
- The approved schedule used to measure and report performance (Correct answer)
- A list of risks that could delay the project
- The minimum staffing requirement for the project
Correct answer: The approved schedule used to measure and report performance
The schedule baseline is the approved version of the project schedule used as the reference for tracking variance.
Question 5: When planning a drafting project, 'predecessor' tasks are those that:
- Follow the current task and depend on its completion
- Must be completed before the current task can begin (Correct answer)
- Can run concurrently with the current task
- Have higher priority than all other tasks
Correct answer: Must be completed before the current task can begin
A predecessor task must be completed (or reach a defined state) before the successor task can start.
Question 6: Schedule compression by adding more resources (such as drafters) to critical path tasks to shorten their duration is called:
- Fast-tracking
- Crashing (Correct answer)
- Resource leveling
- Scope crashing
Correct answer: Crashing
Crashing adds resources to critical path tasks to reduce duration, typically increasing cost but shortening the schedule.
Question 7: In a project schedule, a task on the critical path has total float of:
- Greater than zero
- Exactly zero (Correct answer)
- Negative one or less
- Equal to the project duration
Correct answer: Exactly zero
Tasks on the critical path have zero total float, meaning any delay to them directly delays the project end date.
In PERT (Program Evaluation and Review Technique), the expected time formula uses optimistic (O), pessimistic (P), and most likely (M) estimates.
The formula is: