← All CDT Flashcard Decks

Project Delivery Methods Flashcards

6 cards from real CDT practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 Project Delivery Methods flashcards as text
  1. In a Design-Bid-Build delivery method, what is the sequence of project phases?

    Answer: Design is completed, then bids are solicited, then construction begins

    Design-Bid-Build is the traditional linear sequence: complete design documents, solicit competitive bids, award contract, then construct.

  2. Which project delivery method combines design and construction responsibilities under a single contract with one entity?

    Answer: Design-Build

    In Design-Build, a single entity is responsible for both the design and construction of the project under one contract with the owner.

  3. What is the primary advantage of the Construction Manager at Risk (CMAR) delivery method for an owner?

    Answer: Early contractor involvement with a Guaranteed Maximum Price protecting the owner from cost overruns

    CMAR provides early contractor input during design and a Guaranteed Maximum Price (GMP), capping the owner's construction cost exposure.

  4. In which delivery method does the owner maintain separate contracts with a designer and multiple prime contractors?

    Answer: Multiple Prime

    In a Multiple Prime delivery method, the owner holds separate contracts directly with each prime trade contractor and coordinates between them.

  5. What is a Guaranteed Maximum Price (GMP) in a construction contract?

    Answer: The price ceiling above which the contractor absorbs all additional costs

    A GMP sets the maximum amount the owner will pay; if costs exceed the GMP, the contractor absorbs the overage.

  6. What distinguishes Integrated Project Delivery (IPD) from other delivery methods?

    Answer: A multi-party agreement aligns owner, designer, and contractor incentives with shared risk and reward

    IPD uses a multiparty agreement that aligns owner, architect, and contractor interests through shared risk, reward, and collaborative decision-making from project inception.