CDT - Construction Documents Technologist Practice Test
CDT Construction Administration 3
What triggers the commencement of the contractor's warranty period under AIA A201?
Select your answer
A
The date of final payment
B
The date of issuance of the Certificate of Substantial Completion
C
The date the building permit is issued
D
The date the Notice to Proceed is issued