Which document formally authorizes the existence of a project and grants the project manager authority to apply resources?
Answer: Project charter
The project charter is the document that formally authorizes a project and empowers the project manager to use organizational resources.
A drafting project team is using a Kanban board. Tasks are organized in columns: 'To Do,' 'In Progress,' and 'Done.' This is an example of:
Answer: Visual project management / agile workflow
Kanban boards are a visual agile workflow tool that tracks task status through defined stages, limiting work in progress.
Schedule variance (SV) in Earned Value Management is calculated as:
Answer: Earned Value minus Planned Value
SV = EV - PV; a negative SV means the project is behind schedule relative to planned progress.
A project manager adds two weeks of buffer time at the end of a drafting project to absorb unexpected delays. This buffer is called:
Answer: Contingency reserve
Contingency reserve is planned buffer added to the schedule to handle identified risks and uncertainties.
Which project scheduling approach divides work into fixed-length iterations with regular deliverables?
Answer: Sprint-based (Agile/Scrum) scheduling
Agile/Scrum uses fixed-length sprints (typically 1–4 weeks) to deliver incremental value and adapt to change.
When estimating activity durations for a drafting project, the 'analogous estimating' technique relies on:
Answer: Expert judgment based on similar past projects
Analogous estimating uses historical data from similar previous projects as the basis for estimating current project durations.
A project network diagram shows Task A (5 days) → Task B (3 days) → Task C (4 days) on one path, and Task A (5 days) → Task D (8 days) → Task C (4 days) on another. What is the critical path duration?
Answer: 17 days
Path 1: A(5)+B(3)+C(4)=12 days; Path 2: A(5)+D(8)+C(4)=17 days; the critical path is the longer path at 17 days.