In the triple constraint, if the scope of a trade surveillance project grows while the deadline stays fixed, what most likely has to change?
-
A
Nothing, because the constraints are independent
-
B
Cost or resources must increase, or quality may suffer
-
C
The project charter becomes invalid
-
D
The critical path gets shorter