In a Disciplined Agile context, which technique is MOST effective for identifying all relevant stakeholders at the start of a project?
-
A
Stakeholder register created by the project manager alone
-
B
Collaborative stakeholder mapping workshop with the team
-
C
Email survey sent to department heads
-
D
Review of the organizational chart only