A drafter working on a renovation project finds that field measurements disagree with the archived as-built drawings. What is the best risk-mitigating response?
-
A
Treat verified field measurements as governing, flag the discrepancy, and update the base drawings with a documented note
-
B
Trust the archived as-builts because they are official documents
-
C
Average the two sets of numbers to split the difference
-
D
Proceed with whichever numbers make the layout easier to draw