A drafter discovers a dimensional conflict between the architectural and structural drawings the day before a submission deadline. What is the most appropriate risk mitigation action?
-
A
Document the discrepancy and notify the project lead immediately with a written RFI
-
B
Choose the dimension that seems most likely correct and proceed
-
C
Delete the conflicting dimension from one set so drawings match
-
D
Submit both drawings as-is and address the conflict after the deadline