Which scenario represents a breach of drawing configuration control?
-
A
A shop supervisor pencils a dimension change onto the released print and uses it for production
-
B
A checker redlines a copy during formal review
-
C
An engineer requests an ECO to change a dimension
-
D
A drafter archives the superseded revision