The Performance Measurement Baseline (PMB) in EVM is best described as:
-
A
The sum of all approved change orders
-
B
The time-phased budget plan against which project performance is measured
-
C
The actual cost curve plotted against the project schedule
-
D
The forecasted cost at project completion