CCT Earned Value Management 2 — Questions and Answers
Question 1: Which Estimate at Completion (EAC) formula is used when the current CPI is expected to continue for the remainder of the project?
- EAC = BAC + (BAC - EV)
- EAC = AC + (BAC - EV)
- EAC = BAC / CPI (Correct answer)
- EAC = AC + ETC
Correct answer: EAC = BAC / CPI
When current cost efficiency (CPI) is expected to remain constant, EAC = BAC / CPI, projecting final cost based on how efficiently budget has been used so far.
Question 2: The To-Complete Performance Index (TCPI) based on BAC is calculated as:
- (BAC - EV) / (BAC - AC) (Correct answer)
- (EV - AC) / (BAC - EV)
- (BAC - AC) / (BAC - EV)
- (AC - EV) / (BAC - AC)
Correct answer: (BAC - EV) / (BAC - AC)
TCPI = (BAC - EV) / (BAC - AC); it represents the cost efficiency that must be achieved on remaining work to meet the original budget.
Question 3: What does Variance at Completion (VAC) measure?
- The difference between planned and actual start dates
- The difference between BAC and the Estimate at Completion (Correct answer)
- The ratio of earned value to actual cost
- The total amount of approved changes
Correct answer: The difference between BAC and the Estimate at Completion
VAC = BAC - EAC; it projects how much over or under the original budget the project is expected to finish.
Question 4: If EV = $120,000 and PV = $140,000, what is the Schedule Variance (SV)?
- +$20,000
- -$20,000 (Correct answer)
- +$260,000
- -$260,000
Correct answer: -$20,000
SV = EV - PV = $120,000 - $140,000 = -$20,000, indicating $20,000 worth of planned work has not yet been completed.
Question 5: The Estimate to Complete (ETC) when current CPI is expected to continue is calculated as:
- ETC = BAC - EV
- ETC = (BAC - EV) / CPI (Correct answer)
- ETC = EAC - BAC
- ETC = AC / CPI
Correct answer: ETC = (BAC - EV) / CPI
ETC = (BAC - EV) / CPI estimates the cost to complete remaining work at the current spending efficiency rate.
Question 6: Actual Cost (AC) in EVM terminology is also known as:
- Budgeted Cost of Work Performed (BCWP)
- Budgeted Cost of Work Scheduled (BCWS)
- Actual Cost of Work Performed (ACWP) (Correct answer)
- Estimate to Complete (ETC)
Correct answer: Actual Cost of Work Performed (ACWP)
Actual Cost (AC) is the traditional term ACWP—Actual Cost of Work Performed—representing real expenditures incurred for completed work.
Question 7: A TCPI value greater than 1.0 indicates that:
- The remaining work must be performed more efficiently than current performance (Correct answer)
- The project is under budget and ahead of schedule
- Future work can be performed less efficiently and still meet the budget
- The project has been completed within the approved budget
Correct answer: The remaining work must be performed more efficiently than current performance
A TCPI > 1.0 means the efficiency required to complete remaining work exceeds current performance, indicating the original budget is increasingly difficult to meet.
Which Estimate at Completion (EAC) formula is used when the current CPI is expected to continue for the remainder of the project?