CCT Cost Control & Monitoring 3 — Questions and Answers
Question 1: In Estimate at Completion (EAC) calculations, which formula assumes future work will be performed at the current CPI?
- EAC = AC + (BAC − EV)
- EAC = BAC / CPI (Correct answer)
- EAC = AC + (BAC − EV) / CPI
- EAC = AC + ETC
Correct answer: EAC = BAC / CPI
EAC = BAC / CPI assumes the cost efficiency experienced so far will continue for the remainder of the project.
Question 2: A project's To-Complete Performance Index (TCPI) based on BAC is 1.25. This means the project team must:
- Spend $1.25 for every $1.00 of remaining work
- Complete $1.25 of work for every $1.00 spent going forward (Correct answer)
- Reduce scope by 25% to meet the budget
- Increase resources by 25% immediately
Correct answer: Complete $1.25 of work for every $1.00 spent going forward
TCPI = (BAC − EV) / (BAC − AC); a value of 1.25 means the team must achieve $1.25 of work value for every remaining dollar spent.
Question 3: Which cost monitoring document provides a time-phased allocation of the project budget and serves as the baseline for performance measurement?
- Cost management plan
- Performance measurement baseline (PMB) (Correct answer)
- Work breakdown structure dictionary
- Resource histogram
Correct answer: Performance measurement baseline (PMB)
The Performance Measurement Baseline is the time-phased budget against which project performance is measured and reported.
Question 4: Cost control 'threshold' in project monitoring typically refers to:
- The maximum percentage variance allowed before corrective action is triggered (Correct answer)
- The point at which contingency reserves are fully depleted
- The minimum CPI required for project approval
- The total cost cap imposed by the project sponsor
Correct answer: The maximum percentage variance allowed before corrective action is triggered
A cost threshold defines the acceptable variance limit (e.g., ±10% of budget) beyond which formal corrective action is required.
Question 5: During a cost review, the project team identifies that a subcontractor is consistently billing for more hours than agreed. The FIRST corrective action should be:
- Immediately terminate the subcontract
- Escalate to executive management
- Verify billing records against contract terms and documented deliverables (Correct answer)
- Increase the project contingency reserve
Correct answer: Verify billing records against contract terms and documented deliverables
Before taking action, the project manager should verify facts by comparing billing records against the contract and accepted deliverables.
Question 6: Which type of cost variance analysis compares the cost of completed work to the cost that was budgeted for that same work?
- Actual vs. planned spending variance
- Cost variance (CV) in earned value management (Correct answer)
- Return on investment analysis
- Life-cycle cost comparison
Correct answer: Cost variance (CV) in earned value management
CV = EV − AC, which compares the budgeted cost of work performed to the actual cost of that work.
Question 7: A project using a 'rolling wave planning' approach to cost control will likely have:
- Highly detailed cost estimates for all future work packages from the start
- Detailed near-term estimates with high-level estimates for distant future work (Correct answer)
- Fixed budgets for every task regardless of uncertainty
- No formal cost baseline until all planning is complete
Correct answer: Detailed near-term estimates with high-level estimates for distant future work
Rolling wave planning provides detailed estimates for near-term work and progressively elaborates estimates for future work as more information becomes available.
In Estimate at Completion (EAC) calculations, which formula assumes future work will be performed at the current CPI?