  1. A project has a BAC of $500,000, an EV of $300,000, and an AC of $350,000. What is the Cost Performance Index (CPI)?

    Answer: 0.86

    CPI = EV / AC = $300,000 / $350,000 = 0.857, meaning the project is over budget.

  2. Which cost control technique involves setting a maximum allowable cost for a project element and requiring redesign if that threshold is exceeded?

    Answer: Design-to-cost

    Design-to-cost establishes a cost ceiling for a system or component and drives design choices to stay within that limit.

  3. A Variance at Completion (VAC) of -$40,000 on a project means:

    Answer: The project is forecasted to overrun by $40,000 at completion

    VAC = BAC − EAC; a negative VAC indicates the project is forecast to cost more than its budget at completion.

  4. In a cost monitoring system, a 'cost trend report' primarily serves to:

    Answer: Identify patterns indicating whether costs are improving or deteriorating over time

    A cost trend report tracks cost performance metrics over successive periods to reveal whether the project's cost efficiency is improving or worsening.

  5. Which of the following best describes a 'management reserve' in project cost control?

    Answer: Funds held by management for unknown unknowns outside project scope

    Management reserve covers unknown risks (unknown unknowns) and is controlled by management, not the project manager.

  6. When applying the 50/50 rule for earned value measurement, credit is given as:

    Answer: 50% when started, 50% when complete

    The 50/50 rule awards 50% of the budget when work starts and the remaining 50% only upon completion.

  7. A project manager notices that the SPI has been consistently below 1.0 for the past three periods. This most likely indicates:

    Answer: The project is consistently behind schedule

    SPI = EV / PV; an SPI below 1.0 means less work has been accomplished than planned, indicating a schedule delay.