Cost Control & Monitoring Flashcards
7 cards from real CCT practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Cost Control & Monitoring flashcards as text
A project has a BAC of $500,000, an EV of $300,000, and an AC of $350,000. What is the Cost Performance Index (CPI)?
Answer: 0.86
CPI = EV / AC = $300,000 / $350,000 = 0.857, meaning the project is over budget.
Which cost control technique involves setting a maximum allowable cost for a project element and requiring redesign if that threshold is exceeded?
Answer: Design-to-cost
Design-to-cost establishes a cost ceiling for a system or component and drives design choices to stay within that limit.
A Variance at Completion (VAC) of -$40,000 on a project means:
Answer: The project is forecasted to overrun by $40,000 at completion
VAC = BAC − EAC; a negative VAC indicates the project is forecast to cost more than its budget at completion.
In a cost monitoring system, a 'cost trend report' primarily serves to:
Answer: Identify patterns indicating whether costs are improving or deteriorating over time
A cost trend report tracks cost performance metrics over successive periods to reveal whether the project's cost efficiency is improving or worsening.
Which of the following best describes a 'management reserve' in project cost control?
Answer: Funds held by management for unknown unknowns outside project scope
Management reserve covers unknown risks (unknown unknowns) and is controlled by management, not the project manager.
When applying the 50/50 rule for earned value measurement, credit is given as:
Answer: 50% when started, 50% when complete
The 50/50 rule awards 50% of the budget when work starts and the remaining 50% only upon completion.
A project manager notices that the SPI has been consistently below 1.0 for the past three periods. This most likely indicates:
Answer: The project is consistently behind schedule
SPI = EV / PV; an SPI below 1.0 means less work has been accomplished than planned, indicating a schedule delay.