What should a commissioning provider do when a contractor refuses to correct a documented deficiency?
-
A
Close the deficiency and note it as 'accepted'
-
B
Escalate the issue in writing to the owner and design team
-
C
Remove the item from the issues log
-
D
Perform the correction themselves