The primary purpose of seasonal or deferred testing during the commissioning warranty period is to:
-
A
Satisfy lender requirements for building financing certificates
-
B
Verify system performance under operating conditions not present during initial acceptance testing
-
C
Allow contractors to complete remaining punch list construction items
-
D
Fulfill permit requirements before final certificate of occupancy is issued