CCP Cx Process & ASHRAE Guideline 0 2 — Questions and Answers
Question 1: According to ASHRAE Guideline 0, who is responsible for developing the Owner's Project Requirements (OPR)?
- The commissioning authority (CxA)
- The design engineer of record
- The owner with assistance from the CxA (Correct answer)
- The general contractor
Correct answer: The owner with assistance from the CxA
ASHRAE Guideline 0 assigns responsibility for developing the OPR to the owner, typically with facilitation and assistance from the commissioning authority.
Question 2: During which commissioning phase is the Systems Manual first compiled?
- Pre-design phase
- Design phase
- Construction phase (Correct answer)
- Occupancy and operations phase
Correct answer: Construction phase
The Systems Manual begins to be compiled during the construction phase as equipment is installed and tested, then finalized before occupancy.
Question 3: What is the primary purpose of the Basis of Design (BOD) document in the Cx process?
- To serve as the final construction contract
- To document the design intent and assumptions that fulfill the OPR (Correct answer)
- To outline the contractor's construction schedule
- To define the commissioning authority's fee structure
Correct answer: To document the design intent and assumptions that fulfill the OPR
The BOD documents the design engineer's reasoning, assumptions, and technical approach used to satisfy the Owner's Project Requirements.
Question 4: Which statement best describes the role of 'deferred commissioning' under ASHRAE Guideline 0?
- Commissioning activities postponed due to contractor scheduling conflicts
- Formal Cx tasks that cannot be completed before occupancy and are scheduled for a defined future date (Correct answer)
- Testing that is waived because the system is under manufacturer warranty
- Commissioning of systems installed in a later project phase
Correct answer: Formal Cx tasks that cannot be completed before occupancy and are scheduled for a defined future date
Deferred commissioning refers to Cx activities that cannot be completed before occupancy but are formally documented and scheduled to occur at a specified future date.
Question 5: In the ASHRAE Guideline 0 Cx process, what document formally records deficiencies found during testing?
- Commissioning Plan
- Issues Log (Correct answer)
- Basis of Design
- Systems Manual
Correct answer: Issues Log
The Issues Log (also called a Deficiency Log) tracks all problems identified during commissioning, including their status and resolution.
Question 6: ASHRAE Guideline 0 identifies five commissioning phases. Which phase immediately precedes the Construction phase?
- Pre-design
- Design (Correct answer)
- Occupancy & Operations
- Acceptance
Correct answer: Design
The five phases in order are Pre-design, Design, Construction, Acceptance, and Occupancy & Operations; Design immediately precedes Construction.
Question 7: What is a key CxA deliverable at the end of the Acceptance Phase according to ASHRAE Guideline 0?
- Owner's Project Requirements document
- Final Commissioning Report (Correct answer)
- Commissioning Plan
- Basis of Design update
Correct answer: Final Commissioning Report
The Final Commissioning Report, summarizing all Cx activities, test results, and resolved issues, is the primary CxA deliverable at acceptance phase completion.
According to ASHRAE Guideline 0, who is responsible for developing the Owner's Project Requirements (OPR)?