CCP Cx Plan & Issues Log 2 — Questions and Answers
Question 1: Which section of the Cx Plan defines the roles and responsibilities of the commissioning team members?
- Issues Log
- Commissioning Team Organization (Correct answer)
- Test Procedure Library
- Acceptance Criteria Matrix
Correct answer: Commissioning Team Organization
The Commissioning Team Organization section of the Cx Plan identifies each team member's role, authority, and responsibilities throughout the project.
Question 2: An Issues Log entry is flagged as 'critical' — what distinguishes it from a 'minor' issue?
- It was entered by the CxA rather than a subcontractor
- It affects life safety, building occupancy, or fundamental system operation (Correct answer)
- It requires more than one week to resolve
- It involves equipment costing over $10,000
Correct answer: It affects life safety, building occupancy, or fundamental system operation
Critical issues are those that impact life safety, occupancy, or the fundamental ability of a system to perform its intended function.
Question 3: When should the Cx Plan first be developed on a new construction project?
- After construction documents are 100% complete
- During the design development phase or earlier (Correct answer)
- When equipment submittals are approved
- After the contractor's schedule is finalized
Correct answer: During the design development phase or earlier
The Cx Plan should be initiated during design development or even pre-design to maximize influence over the design and construction process.
Question 4: Which document is most commonly used as the master reference for identifying system performance expectations in the Cx Plan?
- Contractor's submittal log
- Owner's Project Requirements (OPR) (Correct answer)
- Equipment manufacturer's warranty card
- Building permit application
Correct answer: Owner's Project Requirements (OPR)
The Owner's Project Requirements (OPR) defines the performance expectations and goals that the Cx Plan and all commissioning activities are designed to verify.
Question 5: In an Issues Log, what does the field 'responsible party' capture?
- The person who discovered the issue
- The individual or firm accountable for resolving the issue (Correct answer)
- The owner's representative who must approve closure
- The code authority having jurisdiction
Correct answer: The individual or firm accountable for resolving the issue
The 'responsible party' field identifies who is assigned to correct the deficiency, ensuring clear accountability for resolution.
Question 6: A Cx Plan for a large hospital project should include provisions for which of the following that a small office project might omit?
- Equipment submittals review
- Seasonal and integrated systems testing (Correct answer)
- Pre-functional checklists
- Issues Log maintenance
Correct answer: Seasonal and integrated systems testing
Complex facilities like hospitals require seasonal and integrated systems testing to verify performance under varying load conditions not present during a single construction-phase test.
Question 7: Which Issues Log status code indicates that a deficiency has been corrected and verified by the CxA?
- Open
- Resolved-Unverified
- Closed (Correct answer)
- Deferred
Correct answer: Closed
A 'Closed' status means the responsible party has corrected the issue and the CxA has independently verified the correction is acceptable.
Which section of the Cx Plan defines the roles and responsibilities of the commissioning team members?