According to ASHRAE Guideline 0, which document captures the owner's goals, objectives, and criteria that the commissioned systems must meet throughout the facility's life?
-
A
Basis of Design (BOD)
-
B
Owner's Project Requirements (OPR)
-
C
Commissioning Plan
-
D
Systems Manual