In EVM, the term 'over-target baseline' (OTB) refers to:
-
A
A replanned baseline that exceeds the original contract budget
-
B
A baseline set higher than actual costs to motivate the team
-
C
A contingency reserve added above BAC
-
D
An unauthorized scope addition