A contractor proposes a 'shared savings' clause where cost underruns are split 50/50 with the owner. This arrangement primarily shifts which type of risk?
-
A
Schedule risk to the owner
-
B
Cost overrun risk to the contractor
-
C
Cost underrun upside away from the owner
-
D
Quality risk to third parties