A force majeure clause in an international contract typically requires which of the following for a party to be excused from performance?
-
A
The event was unforeseeable, beyond the party's control, and unavoidable
-
B
Any event that increases the cost of performance by more than 10%
-
C
A government declaration of emergency in the seller's country
-
D
Written notice within 30 days of contract signing