A content team is struggling to meet deadlines because scope keeps expanding mid-project. Which practice best addresses this?
-
A
Add more team members immediately
-
B
Implement a formal change control process
-
C
Extend all deadlines by 20%
-
D
Remove the lowest-priority deliverables