A commercial manager notices that actual overhead costs are $15,000 over budget at the midpoint of a project. What is the MOST appropriate immediate action?
-
A
Absorb the variance and continue as planned
-
B
Conduct a root cause analysis and implement corrective measures
-
C
Increase the project budget to cover the overrun
-
D
Report the variance to the client and request additional funding