During contract negotiations, a supplier insists on a 'material adverse change' (MAC) clause. What is the primary purpose of this clause?
-
A
To allow price adjustments based on inflation
-
B
To permit a party to exit the contract if significant negative changes occur to the other party
-
C
To define the scope of work changes
-
D
To establish payment milestones