CCIFP Construction Project Financing and Capital Structure 2 — Questions and Answers
Question 1: Retainage in construction contracts is typically released when:
- The contractor submits the first draw request
- The project reaches 50% completion
- Substantial completion or final completion is achieved (Correct answer)
- The surety bond is issued
Correct answer: Substantial completion or final completion is achieved
Retainage (typically 5–10% withheld from each payment) is released upon substantial or final completion and owner acceptance.
Question 2: Which type of bond guarantees that a construction contractor will complete the project according to contract terms?
- Payment bond
- Performance bond (Correct answer)
- Bid bond
- Maintenance bond
Correct answer: Performance bond
A performance bond protects the project owner by guaranteeing the surety will complete the project if the contractor defaults.
Question 3: Under the percentage-of-completion method, contract revenue is recognized based on:
- Cash received from the owner
- Costs incurred to date divided by total estimated costs (Correct answer)
- Number of months elapsed
- Billings issued to the owner
Correct answer: Costs incurred to date divided by total estimated costs
Revenue is recognized proportionally as the ratio of costs incurred to total estimated contract costs, reflecting work actually performed.
Question 4: A contractor with negative working capital may signal which risk to lenders and sureties?
- Excessive equity investment
- Inability to meet short-term obligations (Correct answer)
- Overly conservative bidding strategy
- Strong project pipeline
Correct answer: Inability to meet short-term obligations
Negative working capital (current liabilities > current assets) indicates the contractor may struggle to pay suppliers, subcontractors, and short-term debts.
Question 5: In construction project financing, a 'completion guarantee' is typically provided by:
- The general contractor to the lender (Correct answer)
- The lender to the project owner
- The subcontractor to the general contractor
- The architect to the owner
Correct answer: The general contractor to the lender
A completion guarantee is a contractor's assurance to the lender that the project will be completed regardless of cost overruns, protecting the lender's collateral.
Question 6: What is the purpose of a joint check agreement in construction financing?
- To allow two lenders to share a single loan
- To ensure payment is made jointly to the contractor and subcontractor/supplier (Correct answer)
- To split project equity between two owners
- To satisfy federal wage requirements
Correct answer: To ensure payment is made jointly to the contractor and subcontractor/supplier
A joint check agreement directs the owner to make payment checks payable to both the GC and sub/supplier, ensuring funds reach lower-tier parties.
Retainage in construction contracts is typically released when: