Under ASC 606, which of the following is NOT a required criterion for recognizing revenue over time for a construction contract?
-
A
The contractor can reliably estimate both the costs to complete and the progress toward completion.
-
B
The customer simultaneously receives and consumes the benefits provided by the contractor's performance.
-
C
The contractor's performance creates or enhances an asset that the customer controls as the asset is created.
-
D
The performance does not create an asset with an alternative use to the contractor, and the contractor has an enforceable right to payment for performance completed to date.