A project manager reviewing a job cost report sees $750,000 in actual costs incurred to date. The report also shows a signed, open subcontract for $300,000 and an issued purchase order for $75,000 for materials not yet delivered. What is the total 'cost to date plus committed costs' for this project?
-
A
A) $750,000
-
B
B) $825,000
-
C
C) $1,050,000
-
D
D) $1,125,000