Which of the following best describes the purpose of a Request for Information (RFI) log maintained by the inspector?
-
A
To track payments made to subcontractors
-
B
To monitor open questions, their submission dates, and response dates to identify schedule impacts
-
C
To record inspector overtime hours
-
D
To catalog material submittals only