When documenting a nonconformance, which element is MOST critical to include so the contractor can take corrective action?
-
A
The inspector's opinion of cause
-
B
A clear description of the deficiency with reference to the violated specification section
-
C
Estimated cost of repair
-
D
A photograph taken from 10 feet away