7 cards from real CCI practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Environmental Compliance flashcards as text
  1. The National Historic Preservation Act (NHPA) Section 106 requires federal agencies to consider effects of their undertakings on properties listed in or eligible for the:

    Answer: National Register of Historic Places

    Section 106 of the NHPA requires federal agencies to consider effects on properties listed in or eligible for the National Register of Historic Places.

  2. A construction inspector observes that concrete washout is being disposed of directly onto bare soil near a drainage ditch. This practice violates which regulatory requirement?

    Answer: NPDES permit conditions prohibiting non-stormwater discharges

    Concrete washout is a non-stormwater discharge that is prohibited from reaching waters of the US under NPDES permit conditions; designated washout areas are required.

  3. Under the EPA's Renovation, Repair and Painting (RRP) Rule (40 CFR Part 745), which type of structure requires certified renovators when lead-based paint is present?

    Answer: Pre-1978 housing and child-occupied facilities

    The RRP Rule applies to pre-1978 housing and child-occupied facilities where renovation may disturb lead-based paint.

  4. Which type of stormwater BMP is classified as a 'source control' measure rather than a 'treatment' measure?

    Answer: Covering and containing material stockpiles to prevent contact with rain

    Covering stockpiles prevents pollutants from being mobilized by rainfall, making it a source control BMP rather than a treatment BMP that captures pollutants after mobilization.

  5. When conducting a pre-construction environmental compliance review, an inspector should verify the project has obtained all necessary permits. Which combination represents the most common suite of environmental permits for a large site-clearing project near wetlands?

    Answer: NPDES CGP, Section 404 Wetland Fill Permit, Section 401 Water Quality Certification

    Large grading projects near wetlands typically require the NPDES CGP for stormwater, a Section 404 permit for wetland impacts, and a Section 401 certification from the state.

  6. An SWPPP requires inspection of BMPs after rainfall events exceeding a specified threshold. Under the EPA's 2017 CGP, how soon after a qualifying precipitation event must an inspection occur?

    Answer: Within 24 hours

    The EPA 2017 CGP requires post-storm inspections within 24 hours of the end of a qualifying precipitation event (typically ≥0.25 inches in 24 hours).

  7. Fugitive dust emissions from grading and earthmoving operations are regulated under which federal law?

    Answer: Clean Air Act

    Fugitive dust (particulate matter) from construction is regulated as an air pollutant under the Clean Air Act, with states implementing dust control requirements.