CCI CCI Quality Control & Assurance 2 — Questions and Answers
Question 1: What is the correct curing temperature range for standard Portland cement concrete to achieve optimal strength gain?
- 50°F to 95°F (10°C to 35°C) (Correct answer)
- 32°F to 50°F (0°C to 10°C)
- Above 95°F (35°C)
- Below 32°F (0°C)
Correct answer: 50°F to 95°F (10°C to 35°C)
ACI 308 specifies that concrete should be maintained between 50°F and 95°F during curing to allow proper hydration and strength development.
Question 2: What is the purpose of pre-installation conferences in a quality control program?
- To ensure all parties understand requirements, materials, and procedures before critical work begins (Correct answer)
- To satisfy a contractual billing milestone
- To allow the inspector to meet project subcontractors for networking
- To review contractor insurance certificates
Correct answer: To ensure all parties understand requirements, materials, and procedures before critical work begins
Pre-installation conferences align the contractor, subcontractor, inspector, and design team on specifications, sequencing, and quality requirements before work starts.
Question 3: During quality control inspection of structural steel bolt installation, what torque verification method uses a calibrated wrench to check installed bolts?
- Turn-of-nut verification or torque-wrench verification per AISC and RCSC specifications (Correct answer)
- Visual inspection of bolt head marks only
- Measuring the bolt protrusion past the nut
- Tapping bolts with a hammer to detect looseness
Correct answer: Turn-of-nut verification or torque-wrench verification per AISC and RCSC specifications
AISC and RCSC require pretensioned bolts to be verified by approved methods including calibrated torque wrench testing or turn-of-nut verification with inspection.
Question 4: What is the key difference between quality control (QC) and quality assurance (QA) in construction?
- QC is performed by the contractor to meet specifications; QA is performed by an independent party to verify compliance (Correct answer)
- QA is done by the contractor; QC is done by the owner
- QC and QA are interchangeable terms with no practical difference
- QA only applies to material testing; QC applies to workmanship
Correct answer: QC is performed by the contractor to meet specifications; QA is performed by an independent party to verify compliance
QC is the contractor's internal self-checking process, while QA is the independent verification by the owner, inspector, or third-party to confirm QC is working.
Question 5: When inspecting fireproofing (spray-applied fire-resistive material) on structural steel, what is the primary measurement the inspector records?
- Dry film thickness using a calibrated depth gauge at required test intervals (Correct answer)
- Color uniformity and surface texture
- Weight of material applied per bag
- Adhesion strength by hand pull test only
Correct answer: Dry film thickness using a calibrated depth gauge at required test intervals
The thickness of applied fireproofing is the critical performance characteristic, measured with a calibrated depth gauge to verify the required hourly fire rating will be achieved.
Question 6: What does ICC/IBC require regarding the qualifications of a Special Inspector for structural welding?
- The inspector must be a Certified Welding Inspector (CWI) per AWS D1.1 or approved equivalent (Correct answer)
- Any licensed contractor may perform structural weld inspection
- A Professional Engineer must personally perform all weld inspections
- No specific credentials are required beyond general construction experience
Correct answer: The inspector must be a Certified Welding Inspector (CWI) per AWS D1.1 or approved equivalent
IBC requires structural weld inspectors to be qualified as a CWI under AWS D1.1 or meet equivalent credentials accepted by the authority having jurisdiction.
What is the correct curing temperature range for standard Portland cement concrete to achieve optimal strength gain?