What is the primary difference between Value Engineering and Cost Cutting?
-
A
Cost cutting focuses on improving function; VE reduces cost only
-
B
VE maintains or improves function while reducing cost; cost cutting may sacrifice function
-
C
VE is applied only during design; cost cutting is applied during construction
-
D
There is no difference between the two approaches