  1. Which cost estimation method relies on historical data and expert judgment?

    Answer: Analogous estimation

    Analogous estimation uses historical project data and expert experience to estimate costs, making it a quick but less precise method.

  2. What is the main purpose of a contingency reserve in budgeting?

    Answer: To cover unforeseen risks and uncertainties

    A contingency reserve is included in the budget to account for unforeseen risks and uncertainties, ensuring financial preparedness for unexpected costs.

  3. Which cost estimation technique uses mathematical models and statistical data?

    Answer: Parametric estimation

    Parametric estimation applies statistical relationships between cost variables to predict costs based on unit measurements, making it efficient and data-driven.

  4. What is the purpose of Earned Value Management (EVM) in cost control?

    Answer: To track project cost efficiency and schedule performance

    Earned Value Management (EVM) helps assess project performance by comparing planned, actual, and earned costs to track cost efficiency and schedule performance.

  5. Which factor is critical in determining an accurate project budget?

    Answer: Scope definition

    Scope definition is crucial to establishing an accurate budget, as unclear or changing project scopes can lead to cost overruns and budget inaccuracies.

  6. What is a key benefit of using a bottom-up estimation approach?

    Answer: It provides highly detailed and accurate cost projections

    Bottom-up estimation provides highly accurate cost projections by breaking down the project into detailed components and estimating each individually.